Forward Pass Sprint

#12
0:0010 activities
ActDurAfterESEF
A3dstart
B2dA+2
C3dA, B+1
D6dC+1, B
E7dB, C+1
F2dC
G7dA, C
H2dG
I6dG+2
J7dI, B, D, E, F+1, H

Fill in Early Start (ES) and Early Finish (EF) for every activity. ES = day the activity can start; EF = ES + duration. At a merge, ES equals the latest finish of all predecessors.